5. SCL1112 Hung Hom MTR Station

Client: MTRC Corporation

Contract No.: SCL Contract 1112

Project Title / Location: Hung Hom Station and Stabling Sidings (Sub-contract No.H2601/SC/027)

Main Contractor: Leighton Contractors (Asia) Limited

Sub-contract Works: Installation of Concrete Jacking Pipe by AVN1650TB

Total Length: 360m

Duration of works : 2014 – 2015

 

Significant Works of TBM Pipe Jacking

There were 3 sections of ID1650mm Sewerage Lining Pipe to be installed at Hung Hom Station and Stabling Sidings of MTRC by using Tunneling Boring Machine AVN1650TB (Herrenknecht) Pipe Jacking Method and each section was approximate 120m.

Three jacking pipe drives have to cross the intermixed and complex geotechnical circumstances. We encountered Artificial Hard material including Diaphragm Wall, Unreinforced Concrete Piles along the pipe jacking length during TBM driving operation. Especially the TBM driven in the “dump Yard” zone, our TBM cutter head has frequently bunted against the hard and tough materials, they could be the abandoned Concrete Blocks, Train Wheel Axels, Car Engine Blocks or Body Parts, etc.

Experienced Engineers, skillful TBM Operators and Workers have been arranged to manage and handle the project, they formed a powerful working team and work with extreme care, step by step to overcome all problems. Through every endeavors we made, the work has been completed as scheduled.